Updates will be made as they become available:
Construction Updates - Week Ending July 2, 2021
Ogden Ave – Resurfacing Project: The contractor installed the first layer (binder course) of asphalt this week. The project's next phase is to adjust the manhole frames to the final grade before the top layer of asphalt is applied, which will occur in the next few weeks. Check back next week for another update.
31st Street Bridge over the Salt Creek Repairs: Only minor work continued this week due to all the rain events. Check back again next week for another update.
Upcoming Village Projects
Road Paving: The Village received a grant to repave Meadowcrest and Woodside between 31st and 29th Street. This project will commence in either late July or early August. We will update this project after the bidding and Board approval.
Water Main Project: The Village will replace an old deteriorated water main along La Grange Road between Garfield and 31st Street and behind the alley on the Northside of 31st between Meadowcrest and La Grange Road. This project will begin in early July. We will update this project after bidding and Board approval.
Permeable Pavement Intersections: The Village received grant funding to construct three Green Infrastructure intersections at Monroe and Community, Robinhood, and Sherwood. This project is in the design phase and should be shovel-ready in late July, with construction commencing in early August. We will update this project after bidding and Board approval.